Since our last newsletter in May, and despite the Covid-19 complications, we have installed and commissioned further sites: All Saints, at Weymouth in May, Beaminster School in September, and our first Dorset Community Healthcare site, Bridport Community Hospital was commissioned on 29th October.
We are especially pleased to have been able to progress installations with Dorset Healthcare despite the pandemic, many thanks to all those at Dorset Healthcare who enabled this.
In summary, we have completed and commissioned 455kW at five sites, have a further 188kW as works in progress at three sites, and are following up further potential sites to deliver the final 57kW.
Complete (455kW) | ||
All Saints School, Weymouth | 61kW | May 2020 |
Beaminster School | 112kW | August 2020 |
Bridport Community Hospital | 99kW | October 2020 |
The Blandford School | 85kW | February 2020 |
Wey Valley School, Weymouth | 97kW | February 2020 |
In progress (188kW) | ||
Alderney Hospital | 97kW | Expected November 2020 |
Blandford Community Hospital | 50kW | Expected November 2020 |
Sturrminster Newton High School | 41kW | TBC |